BEMIDJI -- Road work will start on 30th Street Northwest and Hannah Avenue on Monday, July 8, weather permitting.

According to a release from the city, Reierson Construction is the contractor on the project, which is expected to be completed by the end of September.

The project will reconstruct 30th Street from Hannah Avenue to Ridgeway Avenue and Hannah Avenue from Paul Bunyan Drive to 30th Street. The project will involve the removal and replacement of pavement and aggregate material, installing new water main, sanitary sewer, storm sewer, curb and gutter. It also includes adding a 10-foot paved trail on 30th Street and a 6-foot concrete sidewalk on Hannah Avenue.

For more information, contact the city of Bemidji Engineering Department at (218) 333-1850.