Bemidji road construction projects under way

Email Sign up for Breaking News Alerts

news Bemidji, 56619

Bemidji Minnesota P.O. Box 455 56619

BEMIDJI — The city of Bemidji has begun the 2013 State Aid Bituminous Removal & Resurfacing Project 7 a.m. to 7 p.m. Mondays through Fridays and some Saturdays as of yesterday and is expected to last until Aug. 6.

Advertisement
Advertisement

The streets included are:

- 15th St. NW (Irvine Ave. NW to CSAH 6)

- Roosevelt Rd. SE (Washington Ave. S to Paul Bunyan Dr. SE)

- Pioneer St. SE and Industrial Park Dr. SE (Washington Ave. S to Mahnomen Dr. SE)

The streets will be closed to traffic during working hours but access to residences and business will be maintained after work hours and as best as possible during working hours. 